Skip to content
Luminesca.
Analysis · A closer look

Why 2,000+ GW of New Power Is Stuck in a Queue — and What the Interconnection Bottleneck Means for the Grid

The U.S. grid has a strange problem: there is far more power ready to be built than the grid can absorb quickly. At the end of 2024, roughly 10,300 generation and storage projects — about 2,300 GW of capacity — were waiting in interconnection queues, a backlog nearly twice the country's entire installed generating fleet. Only a fraction will ever get built, and the wait has stretched past four years. Here is why the queue exists, why it matters now that electricity demand is finally surging, and what reform is — and isn't — fixing.

What an interconnection queue actually is

To connect a large power plant — a solar farm, a wind project, a battery, or a gas turbine — to the high-voltage transmission grid, a developer must file an interconnection request. The grid operator then runs a series of impact studies to figure out what new equipment or upgrades are needed before the project can safely plug in, and assigns the cost of those upgrades. The list of projects working their way through that study process is the interconnection queue. For most of the past two decades the process was first-come, first-served and serial: one project at a time, in the order it arrived. That design worked when queues were short. It broke down as renewables, storage and now data-center-driven demand flooded in.

How big the backlog got

Berkeley Lab's annual "Queued Up" tracking, compiled with Interconnection.fyi from nearly all U.S. grid operators, puts about 10,300 projects and roughly 2,300 GW of capacity actively seeking connection at the end of 2024 — roughly 1,400 GW of generation plus about 890 GW of storage. The backlog peaked near 2,600 GW at the end of 2023. By 2025 the active total had eased to about 2,061 GW as withdrawals surged past 750 GW in a single year. The mix at the end of 2024 was dominated by solar (about 956 GW), storage (about 890 GW) and wind (about 271 GW), with natural gas capacity jumping 72% year-over-year to 136 GW — a signal that data-center and firm-power demand is pulling gas back into the queue, not just clean energy.

Why projects wait so long — and why most never connect

The wait has quietly doubled. Berkeley Lab finds the median time from interconnection request to commercial operation rose from under two years for projects built in 2000–2007 to more than four years for those built in 2018–2024. And the sobering part: of the capacity that requested interconnection between 2000 and 2019, only 13% had reached commercial operation by the end of 2024; 77% had been withdrawn and 10% was still active. Filing a queue position is cheap relative to actually building a plant, so many developers stake a claim years early, then drop out when land, permits, power-purchase agreements, equipment or financing don't line up — or when the transmission upgrade bill proves too steep.

Why it matters now: demand is finally surging

For twenty years U.S. electricity demand was nearly flat, which is why a slow queue was an annoyance rather than a crisis. That has changed. NERC's 2025 Long-Term Reliability Assessment projects summer peak demand to grow 224 GW over the next ten years — 69% above its prior forecast — with winter demand growing a further 246 GW. Data centers, artificial intelligence and the broader digital economy account for most of the increase. The assessment flags 13 of 23 assessment areas at risk of resource-adequacy challenges within five years, with five regions — MISO, PJM, ERCOT and two WECC subregions — at "high risk" by 2030 and possible shortfalls as early as 2028. NERC's John Moura is careful to frame it as "not a prediction of failure but an early warning on the trajectory of risk." The paradox is sharp: the very projects needed to meet the new demand are stuck in the queue that is slowest to process them.

What reform is doing: FERC Order 2023

The central fix is FERC Order 2023, issued in July 2023 and phased in through 2024. It attacks the bottleneck on three fronts: it replaces serial studies with first-ready, first-served cluster studies that evaluate many projects at once; it removes the old "reasonable efforts" standard and adds penalties when transmission providers miss study deadlines; and it folds in advanced transmission technologies and inverter-based-resource modeling. To flush out speculation, it raises financial commitments — bigger study deposits, site-control and commercial-readiness requirements — and penalizes withdrawn requests. FERC Chair Willie Phillips noted at the time that projects faced an average wait of up to five years. Early signals are encouraging: several grid operators set records for executed interconnection agreements in 2025, with CAISO and ERCOT each clearing more than 30 GW of signed agreements.

The bottom line: reform is bending the curve, not breaking it

The 2025 data shows the reform beginning to bite — withdrawals of speculative projects are up, and the volume of newly executed interconnection agreements is rising in most regions with data. But queue timelines remain long, and demand growth is now the wild card it wasn't a decade ago. The metrics worth watching are cluster-study throughput, how fast data-center loads actually interconnect, the pace of regional transmission buildout, and how mature Order 2023 implementation becomes in each operator's territory. The queue is no longer an obscure plumbing problem; it is one of the main gates between today's record volumes of ready-to-build projects and a grid that can keep the lights on as load accelerates.

Visual Highlights

Frequently Asked Questions

What is an electricity interconnection queue?

An interconnection queue is the waiting list a grid operator maintains for proposed power plants that want to connect to the transmission system. Before a solar, wind, storage or gas project can plug in, the transmission provider runs impact studies to determine what new equipment or upgrades are needed and assigns the costs. Developers apply by filing an interconnection request, and that request sits in the queue until studies are complete and an interconnection agreement is signed.

Why do so few queued projects actually get built?

Entering a queue is only one early step in a long development process. Berkeley Lab's "Queued Up" tracking shows that of the capacity that requested interconnection between 2000 and 2019, only 13% had reached commercial operation by the end of 2024, while 77% had been withdrawn and 10% was still active. Projects also need land, permits, power-purchase agreements, equipment and financing, and may face costly transmission upgrade requirements — and because filing is relatively cheap, many speculative projects enter the queue years before they are viable.

How is FERC Order 2023 supposed to help?

FERC Order 2023, issued in July 2023, reforms interconnection in three ways: it replaces slow first-come, first-served serial studies with first-ready, first-served cluster studies that evaluate many projects at once; it removes the "reasonable efforts" standard and adds penalties when transmission providers miss study deadlines; and it incorporates advanced transmission technologies and inverter-based-resource modeling. It also raises financial commitments — larger deposits, site control and commercial-readiness requirements — to deter speculative entries, and penalizes withdrawn requests. Early signs are positive: several grid operators set records for executed interconnection agreements in 2025.

Why does the queue bottleneck matter for grid reliability right now?

Because electricity demand is rising sharply for the first time in decades. NERC's 2025 Long-Term Reliability Assessment projects summer peak demand to grow 224 GW over 10 years — 69% above its prior forecast — with data centers and the digital economy accounting for most of the increase. The catch is that the projects needed to meet that demand are stuck in the very queue that is slow to process them. NERC flags 13 of 23 assessment areas at risk of resource-adequacy challenges within five years, with possible shortfalls as early as 2028 in some regions.

Sources: DOE Grid · EIA · LBNL — editorial summary compiled from the official resources above (captured 2026-08-15)
This page is an informational compilation. For reference only — please refer to each source’s official documentation.

For reference only — please refer to each source’s official documentation.

For reference only — please refer to each source's official reporting.

Images: Pexels (free license) · Photos by contributors on Pexels.
Privacy Policy · Contact